Minor Project Schedule 2009

OCTOBER

Friday 23rd
Statement of intent deadline.

Thursday 29th
Spend day testing projectors with test film, mock up temporary screen (AM) and finalise production details i.e. subjects, locations, shot narrative. (PM)
Contact airports re: scanners and film.

Friday 30th (day) / Saturday 31st (day)
Get SUPER8 camera off Aaron Kay, book space for the crit. Work on dissertation to offset Tuesday and Wednesday in Germany.

NOVEMBER

Tuesday 3rd & Wednesday 4th
Germany trip, shoot first narrative and footage while on the move.

Thursday 5th
Finish both narratives and rap shooting

Friday 6th
Submit film for processing in the morning *MUST BE BEFORE 2PM*
(Contingency plan: 1 week processing

Weekend of 7th & 8th
Buying / collecting all materials needed for constructing installation

Thursday 12th / Friday 13th / Saturday 14th
Solid building / Code / Testing for moving projectors with screen (use test film)

Thursday 19th
Solid building, finalising code

Friday 20th
Get film back from Windscreen Centre, create loop and test to find timings.

Saturday 21st / Sunday 22nd
Alter build and code according to findings from testing, possibly add in 2 x servos to regulate sync of film

Wednesday PM / Thursday
Complete testing and build, fully set up and allow to run. Make adjustments.

Friday 27th - 2PM (CONFIRM):
FINAL DEADLINE

No comments:

Post a Comment